Terminal Unit and Energy Recovery Unit Replacement - 402 Social Sciences Building

Scheduled Maintenance Report for Kennesaw State University

Update

Scheduled maintenance is still in progress. We will provide updates as necessary.
Posted Jul 22, 2025 - 13:44 EDT

Update

Updated Schedule:
July 21- TU installation begins on the 3rd floor, 6am -6pm, Monday – Saturday.
July 25 - TU demolition begins on the 2nd floor with completion by July 31.
Aug 1 - TU demolition begins on the 1st floor with completion by Aug 7.
Aug 7 - TU demolition will begin on the 4th floor with completion by Aug 13.
Aug 13 - TU demo & installation 5th floor, if the project is on schedule for Aug 16 completion. Alternatively, this will be scheduled during Thanksgiving break or during the weekends

Impact: The project will increase temperature levels, as the HVAC system will be offline during installation. Sections of the ceiling will be exposed and may reveal some mechanical components. Noise levels associated with the project are expected to be minimal.
Posted Jul 18, 2025 - 13:53 EDT

Update

Bartow Avenue is now open.
Posted Jul 10, 2025 - 12:04 EDT

Update

Crane operations are now completed. Floors 4 and 5 are now accessible and can resume normal activities. All entrances on the first floor are open. Please be advised that Bartow Avenue will remain closed until the crane has been removed from the roadway. A notification will be issued once the street reopens.
Posted Jul 09, 2025 - 09:53 EDT

Update

Updated timeline for the TU and ERU project.
- June 30 – TU demolition will begin on the 3rd floor and the main air handler for the floor will be turned off and will be turned on by July 10.
-July 7 – Bartow Avenue will be closed for the crane and equipment to arrival.
-July 8 – 9, Crane work begins, the 4th and 5th floors must be vacated to accommodate ERU crane lift.
- July 14 -15, Crane work resumes, 4th and 5th floors must be vacated to accommodate ERU crane lift.
-July 21 - TU installation begins on the 3rd floor, 6am -6pm, Monday – Saturday
-July 25 - TU demolition begins on the 2nd floor with completion by July 31st.
-Aug 1st - TU demolition begins on the 5th floor with completion by Aug 7th
-Aug 7th - TU demolition will begin on the 4th floor with completion by Aug 13th
-Aug 13th - TU demo & installation 1st floor, IF on schedule for Aug 16th completion. Alternate schedule will be Thanksgiving or weekends
Posted Jul 08, 2025 - 10:50 EDT

Update

Bartow Avenue will be closed for the crane and equipment to arrive and set up on Bartow Avenue for the Energy Recovery Unit (ERU) replacement project.
Posted Jul 07, 2025 - 07:42 EDT

Update

TU demolition will begin on the 3rd floor and the main air handler for the floor will be turned off and will be turned on by July 10.
Posted Jun 30, 2025 - 08:08 EDT

Update

Terminal Unit (TU) replacement began today with floor protection and ceiling removal on the 5th floor, progressing downward through the building.
Posted Jun 23, 2025 - 13:49 EDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 23, 2025 - 07:00 EDT

Scheduled

We will be performing major scheduled utility maintenance at 402 Social Sciences starting on June 23 through August 7.
Impact: This project involves replacing the Terminal Units and the Energy Recovery Unit for the building. The project will be taking place at the Social Sciences building, but other surrounding areas including Bartow Avenue and the Visual Arts Loading Dock areas will be impacted.
On June 23, the Terminal Unit replacement will begin with floor protection and ceiling removal on the fifth floor, progressing downward through the building.
From June 30 through August 7, TU demolition will be taking place on a different floor each week. During this time, the main air handler for the floor will be turned off.
From July 7-9, Bartow Avenue will be closed due to the crane and other equipment that will be used to install the new Energy Recovery Unit. On July 8-9, the 4th and 5th floors will need to be vacated.
Posted Jun 17, 2025 - 08:19 EDT
This scheduled maintenance affects: Utilities & Engineering Services Kennesaw (Campus Electrical System).